- The meeting reviewed KPI proposals, the HVN contract (Exhibit A), SixPeak asset-manager submission and mobilization timing for HVN/LV sites.
- Participants confirmed decisions and outstanding items to resolve offline.
- KPI discussion: The team reviewed five proposed KPIs—schedule milestone attainment, buyout savings, subcontractor performance, safety performance, and construction team workload—and agreed they are sensible but need a practical monthly tracking approach.
- Grady and Pedro proposed a simple subcontractor ranking using two to three inputs (scheduling, inspection, billing) and suggested field supers provide repeat feedback.
- The group accepted a primitive initial system while building formal tracking this quarter or month.
- Chris requested KPI materials be uploaded to Box and mirrored on the LV board portal for leadership reporting.
- Contract and Exhibit A: Chris noted he drafted Exhibit A from templates and sent it to Michael for revision; Derek asked for clarity on Michael’s pollution-coverage additions.
- Grady highlighted variable city-specific requirements.
- Derek committed to review Michael’s comments and swap Exhibit A in the sent contract if appropriate.
- Resolution of Exhibit A and finalizing the HVN contract remain open and will be handled offline.
- SixPeak and financing: Chris reported he and Skylar are preparing a SixPeak submission to be considered as the strategy’s asset manager; materials will be presented to Skylar’s father.
- Fundraising is targeted to begin after Labor Day, with a capital close expected in October or November.
- Resourcing and mobilization: The group agreed senior construction leadership must be hired to manage expanded development, while the current team remains responsible for early delivery until hires are made.
- Grady reviewed HVN site timing and mobilization needs and requested a definitive LV start date to schedule shoring and subcontractors; targets discussed were mid-August to September and a closing statement/notice to proceed is required to enable mobilization.
- Open items and unresolved issues: Finalize Exhibit A and contract language with Michael’s pollution-coverage input, complete the SixPeak submission materials, confirm KPI tracking implementation and data placement in Box/LV portal, and set a definitive LV start/notice-to-proceed to trigger mobilization.